GTC works

Gas in multiple-occupancy buildings works

Update 26/01/26 –

MG Contracts in collaboration with GTC are progressing well with the work to ensure
remediation of the findings from the GTC Surveys across the development with regular
updates being provided to the factor and committee. This work is now complete within
the first 10 stairs on the development and compliance sign off has been received from
GTC for these.

Work has been completed in the following stairs

  • 1 – 2 Sinclair Place
  • 24 – 30 Sinclair Place
  • 32 Sinclair Place

A range of works to ensure the compliance of the shared areas of each stair is being
undertaken as per previous communications including

  • Seal any gaps within utilities shafts to prevent gas leaking into voids including
    behind internal stair walls.
  • Seal tops of all shafts to prevent gas leaking into attic space.
  • Seal all ingress points where utilities have entered dwellings (e.g. broadband
    cables)
  • Remove all debris from shafts.
  • Install ventilation panels in doors to remove risk of gas build up within the shaft
    (intention is to limit these to ground and top floor but may be required at each
    level in some instances)
  • Ensure separation of electrical cables from gas supply pipes including
    installation of rubber installation material where suitable physical gaps are not
    possible.

Work will also take place in the communal supply cupboards which are located on the
ground floor (usually under the stairs)..

  • Activities will include each of the above activities however also ensure sealing of
    access to building foundation areas to prevent a gas build up in this space.

A record of works has been taken during the works and shared with the factor and GTC
allowing for compliance and completion of remedial works to be signed off. These are
being retained for reference during future compliance checks.

Examples of completed works as follows

Upon completion of works in each stair notices are being placed within the respective
areas / shaft doors advising of compliance, ongoing requirements and ensuring any
future works in this area are undertaken to appropriate standards.


The schedule for remaining work is as follows

BlockStart DateDuration
18 Sinclair PlaceMarch ’262.5 days
19 Sinclair PlaceMarch ’264 days
20 Sinclair PlaceMarch ’263.5 days
3 Sinclair PlaceMarch ’262 days
4 Sinclair PlaceMarch ’263.5 days
5 Sinclair PlaceMarch ’264 days
6 Sinclair PlaceMarch ’263.5 days
1 Sinclair GardensApril ’262 days
2 Sinclair GardensApril ’262 days
3 Sinclair GardensApril ’262 days
4 Sinclair GardensApril ’263.5 days
5 Sinclair GardensApril ’262 days
1 Sinclair CloseMay ’262 days
2 Sinclair CloseMay ’263.5 days
3 Sinclair CloseMay ’262 days
4 Sinclair CloseMay ’262 days
5 Sinclair CloseMay ’263.5 days
6 Sinclair CloseMay ’262 days
31 Sinclair Place TBC*TBC*
*31 Sinclair Place is subject to some additional works undertaken directly by GTC
prior to commencement of the remedial work by our contractors

Updates on this schedule including specific dates will be provided nearer the time and
be communicated out to individual stairs and also on this webpage.

Any questions should be directed to

Leave a Reply

Your email address will not be published. Required fields are marked *